General Court dismissed the application challenging classification of Øresund fixed-link guarantees as existing State aid  

In February 2024, the Commission adopted Decision (EU) 2024/2467 on the measures State aid SA.52162 – Denmark and State aid SA.52617 – Sweden implemented by Denmark and Sweden in which it considered inter alia that the State guarantee model granted by the Kingdom of Denmark and the Kingdom of Sweden for the purpose of financing the planning and construction of a fixed link across the Øresund constituted aid and that that aid should be classified as existing aid not subject to recovery. The applicants, ferry operators competing with the fixed link, relied on two arguments. They firstly argued that the Commission made a mistake by qualifying the measure as a single individual measure. In their view, it should have considered that a separate aid measure was granted each time a financial transaction entered by the consortium was guaranteed. Secondly, they argued that the limitation period should restart on each such occasion. 

The General Court rejected both arguments. Firstly, these guarantees formed part of a comprehensive agreement; the various financial transactions, pursued the same objective and were sufficiently closely linked to be regarded as inseparable. Secondly, it considered that the advantage granted was the consortium’s unconditional right to obtain State guarantees without a market premium. The advantage has therefore been ongoing since the consortium was established and should not be regarded as a series of advantages. The General Court considered the measure to have been granted in 1992 and, consequently, to constitute existing aid. 

As for the argument that the aid constituted operating aid, it was considered irrelevant as the aid was existing aid. 

For more information, see the General Court’s judgment.